Update---08/01/14 -
We received a $12,.0000 grant from Eastern Pennyslvania Youth Soccer Association that will be used to pay for the Northampton County review of our plans.  We are still working on additional grant applications and trying to raise money/donations to complete this project. 


Update---01/23/14 -
We have received final approval from Forks Township Planning Commission and Board of Supervisors.  We now have the green light to make our final submission to Northampton County and to begin construction.  This is great news!  We are currently obtaining quotes for all aspects of the construction project and are seeking monetary and work in kind donations to make our plans a reality.  We will begin a major Fundraising Campaign in the coming month and we are also applying for a grant through the EPYSA.  If you can help in any way please contact us: [email protected]


Update---01/01/2013
- Zoning Hearing went well and we were given approval to submit development plans.  We are on to phase 2 now! 

New Fields at Riverview Estates:

As some of you may already know, ENCO has been working for some time towards development of additional soccer fields for our rapidly growing club.   The property is located on Winchester Drive approximately 1/8 mile from the Golf Course Pro Shop (adjacent to the future driving range) in Riverview estates. 

Development of this additional field space has been an ongoing project for ENCO, and while the development of soccer fields may sound like a simple project, in actuality it is a fairly large project that requires, engineering, site plans, township and county approvals.  Development of these additional fields are vital to the long term success and  growth of ENCO United Soccer Club. 

This project is moving forward in three phases….          
Phase 1 (our current phase) Initial Engineering and preliminary site plan development (complete) Zoning Application and Zoning Hearing to approve the development of soccer fields at this location (to occur early this winter)

Phase 2 (if Zoning is approved) Additional engineering including water conservation studies and fully detailed site plans including water runoff plans. Review of Site Plans by Forks Township and Northampton County Engineering Departments.

Phase 3 Excavation and Grass Planting